TSB Document:

Affected Component: EQUIPMENT ADAPTIVE/MOBILITY

Summary
THIS TECHNICAL BULLETIN PROVIDES A PROCEDURE TO REPLACE THE AFFECTED CNG TANK VALVE TO CORRECT A CUSTOMER CONCERN OF CNG GAS VENTING, LEAKING, OR RELEASING DURING EXTREME COLD TEMPERATURES AND/OR DURING REFUELING DUE TO COLD TEMPERATURES ALONG WITH THE COOLING EFFECTS OF THE REFUELING PROCESS.

Click a tab for more information.

Date Published
APR 18, 2016
NHTSA TSB #
10078505
Find something helpful? Spread the word.

Become a Fan & Spread the Word